项目管理专业人士资格认证(PMP)题库(1459题)


产品负责人不定期参加演示仪式。因此,演示仪式不断被重新安排,工作也会受到多方面的影响。项目经理认为产品负责人没有对项目负责。项目经理应该做些什么来避免这种情况?A product owner Goes not regularly attend demonstration ceremonies. As a result, the demonstration ceremonies are constantly rescheduled and the work is impacted in multiple ways. The project manager believes the product owner is not committed to the project. What should the project manager have done to avoid this situation?


A.定义了一组外部审计,可以向项目发起人公开这种情况。Defined a set of external audits that can expose this situation to the project sponsor.

B.在适当的项目治理级别上与产品负责人达成一致。Agreed with the product owner on appropriate project governance levels.

C.设置“已完成”(DoD)的定义,如果没有另外指定,则认为工作已完成。Set a definition of done (DoD) that considers the work as done if not otherwise specified.

D.要求另一位产品负责人代表产品负责人参加演示。Asked another product owner to attend the demonstrations on behalf of the product owner.


知识点:PMP强化练习题(二)


参考答案:B


解析:PO不参加演示会意味着产品增量无人验收,因此需要该人员参与,其职责和角色需要进行澄清,所以选择B;选项A错误,外部审计通常用于验证项目的合规性和执行效率。选项C错误,设置DoD依然需要产品负责人评审。选项D错误,这不是一个可靠的解决方案,可能会造成角色职责混乱。

进入考试题库