一个敏捷项目正在进行10次迭代中的第5次。在最后一次回顾性检查后,团队成员意识到他们必须加班加点才能完成承诺的工作,项目经理应该怎么做?An agile project is currently undergoing the fifth out of 10 iterations. After the last retrospective inspection, team members realized that they had to work overtime to complete the promised work. What should the project manager do?
A.要求增加团队成员以保持速度。Ask for additional team members to maintain the velocity
B.在迭代中实施一个检查点,以验证团队是否在轨道上。Implement a checkpoint in the iteration to verify if the team is on track
C.进行重点回顾,帮助团队发现根本原因。Conduct a focused retrospective to help the team to discover the root cause
D.要求团队在下个迭代中降低承诺。Ask the team to have a lower commitment for the next iteration
参考答案:C
解析:根据题干,团队承诺与实际进展出现了问题,在采取任何行动前确定问题的根本原因至关重要。通过回顾有助于帮助团队发现潜在问题,并提供讨论潜在解决方案的机会。