在项目执行过程中,项目经理观察到速度较慢,测试队列中的任务量很大。该项目采用的是混合方法,并且只剩下几个迭代。项目经理应该怎么做?During project execution, the project manager observes lower velocity and a high volume of tasks i n the testing queue. The project is using a hybrid approach and there are only a few sprints remaini ng. What should the project manager do?


A.为所有项目团队成员提供测试培训。Provide testing training to all the project team members.

B.向团队中添加一个具有测试技能的新资源。Add a new resource with testing skills to the team.

C.与团队合作了解并解决问题。Work with the team to understand and solve the issues.

D.增加迭代的持续时间,以便完成测试。 Increase the sprint duration so the testing can be completed.


知识点:PMP强化练习题(二)


参考答案:C


解析:混合项目中,自组织团队成员都需要对项目的成功交付负责,遇到问题,大家首选协作解决,选C。