一个高级管理团队成员联系了一名敏捷项目负责人,提到他认为应该包括在当前发布中的某些功能未被包括。敏捷项目负责人应该采取什么行动?A senior management team member contacts an agile project lead and mentions that certain featu res the senior manager thought would be in the c urrent release were not included. What should th e agile project lead do?
A.将产品路线图发送给高级管理成员。Send the product roadmap to the senior manager.
B.向高级管理成员保证这些功能将在下一个迭代中实现。Assure the senior manager that these features will be queued up in the next sprint.
C.邀请高级管理成员参加下一个规划会。Invite the senior manager to the next planning meeting.
D.与团队会面,了解为什么未包括高级管理成员认为的功能。Meet with the team to understand why the senior manager's features were not included.
参考答案:D
解析:干系人提出问题时,项目负责人首先需要背后的原因,这样可以明确地向高级经理解释为什么某些功能未被包含,以及未来的计划。选D。