在一个站立会议中,一个团队成员已经连续五天提供相同的更新。这项任务位于关键路径上,现在有可能导致进度延迟。项目经理应该怎么做?In a stand-up meeting, a team member had provided the same update five days in a row. This task is on a critical path and now has the potential to cause delays. What should a project manager do?
A.通知项目发起人关于延迟的情况。Keep the project sponsor informed about the delay.
B.将任务重新分配给团队的另一个成员。Reassign the task to another member of the team.
C.通过提供额外的资源来支持团队成员立即完成任务。Support the team member by providing one more resource to complete the task immediately.
D.询问团队成员是否存在障碍,并帮助移除障碍。Ask the team member if there is an impediment, and help to remove the blockers.
参考答案:D
解析:项目经理应帮助团队成员消除障碍。根据题干,团队成员已连续几天在站会中提供相同的更新,这一般意味着他们遇到了某种阻碍或问题,导致任务无法继续。项目经理的首要任务是与团队成员沟通,了解是否存在障碍,以帮助团队成员顺利完成任务。