项目经理确定了两个团队成员之间的一个问题,该问题在项目的第二次迭代期间影响了其中一个可交付物的开发。项目经理应该如何处理这个问题以避免对项目产生任何影响?A project manager identifies an issue between two team members that is affecting the development of one of the deliverables during the second iteration of a project. How should the project manager address this issue to avoid any impact to the project?
A.联系职能经理,要求替换冲突的团队成员。Contact the functional managers to request substitutes for the conflicting team members.
B.向两名团队成员发出警告,指出如果问题继续存在,两名成员将从项目中删除。Send a warning to both team members indicating that if the issue continues, both will be removed from the project.
C.与双方团队成员安排一次会议,以了解问题并促成一个令双方都满意的解决方案。Schedule a meeting with both team members to understand the issue and facilitate a solution that satisfies both parties.
D.将双方的团队成员升级到各自的职能经理,并让他们采取适当的行动。Escalate both team members to their respective functional managers and let them take the appropriate actions.
参考答案:C
解析:解决冲突的最佳方式是合作/解决,选C。