一个开发大型水电站的项目正处于实施阶段,并采用混合方法进行管理。项目经理应该做什么来确保在执行阶段完全符合质量要求?A project to develop a large hydropower station is currently in the implementation stage and is managed using a hybrid approach. What should a project manager do to ensure full compliance with quality requirements during the execution phase?
A.分析质量要求Analysis quality requirements
B.规划质量管理Planning Quality Management
C.持续检查可交付物的质量Continuously checking the quality of deliverables
D.建立质量方针和程序Establish quality policies and procedures
参考答案:C
解析:关键词“执行阶段”,在执行阶段,项目经理必须持续监控和评估可交付成果的质量,以确保它们与质量要求保持一致。ABD通常发生在规划阶段。