开发银行产品的项目正处于执行阶段,政府的新法规对产品开发产生了重大影响,干系人关心计划的利益是否仍然有效和可实现。项目经理应该首先做什么?The project to develop bank products is currently in the execution stage, and new government regulations have had a significant impact on product development. Stakeholders are concerned about whether the benefits of the plan are still effective and achievable. What should a project manager do first?


A.重新验证并重新预测收益基准和目标Revalidate and repredict revenue benchmarks and targets

B.将问题上报给发起人并请求更多资金Report the issue to the initiator and request more funding

C.展示实现目标的进度并重新验证项目工作计划Show progress towards achieving goals and revalidate project work plan

D.优化干系人需求和项目目标之间的一致性Optimize consistency between stakeholder needs and project objectives


知识点:PMP强化练习题(二)


参考答案:A


解析:根据题干,干系人关心计划的利益在新法规下是否仍然有效和可实现,合规大于天,这时最好的措施是在新法规下,重新审视和预测项目的收益基准和目标,选A。