在测试新的网络基础设施时,供应商发现由于存在潜在硬件缺陷,一个组件必须升级。为确保团队有效参与项目,项目经理应该怎么做?
When testing a new network infrastructure, the supplier finds that a component must be upgraded due to potential hardware defect. What should the project manager do to ensure that the team is effectively involved in the project?


A.生成变更请求 To generate a change request

B.执行优势、劣势、机会与威胁(SWOT分析) To perform the Strengths, Weaknesses, Opportunities and Threats (SWOT) Analysis

C.更新执行、负责、咨询和知情(RACI)矩阵 Update Responsible, Accountable, Consulted, and Informed (RACI) Matrix

D.修订干系人登记册 To revise the Register of Stakeholders


知识点:PMP强化练习题(二)


参考答案:C


解析:PMBOK(6),P317,9.1.2.2责任分配矩阵。为了确保一件事必须有人在负责,需要更新责任分配矩阵,给每个人确定职责,这样才会确保团队有效参与。其他选项:A目前没必要变更。B是识别风险,不合题意。D非干系人问题。