—个软件升级项目的首席开发人员提出一些增强功能建议,认为这些增强功能会改进项目整体实施和最终用户体验。项目经理应该怎么做?
A lead developer on a software upgrade project suggests enhancements they believe will improve the project’s overall implementation and end-user experience. What should the project manager do?
A.提交变更请求 Submit a change request.
B.确定对进度计划和成本的影响,评估该变更的可行性 Determine the impact on the schedule and cost to assess the change’s feasibility.
C.与项目干系人开会,确定是否应该包含这些增强功能 Meet with stakeholders to determine if the enhancements should be include
D.批准建议的增强功能 Approve the suggested enhancements.
参考答案:B
解析:PMBOK(6),P113,4.6实施整体变更控制。 “开发人员”是内部人员, 团队内部提出变更(发现问题),现分析影响,然后再提交变更其他选项:先B再A,然后考虑C,D。