项目经理正在领导一个涉及跨职能需求和变更的新项目,一些关键干系人正在抵制这些变更,项目经理应该做什么?
A project manager is leading a new project that involved cross-functionalrequirements and changes. Some key stakeholders are resisting the changes. What should the project manager do?
A.收集干系人需求 Gather stakeholder requirements.
B.请项目管理办公室(PMO)协助 Ask the project management office(PMO) for assistance.
C.举行引导式研讨会 Conduct a facilitation workshop.
D.计划团队建设练习 Plan a team-building exercise.
参考答案:C
解析:PMBOK(6)P145- 5.2.2.6 引导。引导式研讨会就是定义跨职能的需求并协调干系人需求差异的。