一个项目开始时,项目经理必须准备一份快速、高层级的成本估算,该项目经理之前管理过一个具有类似规模和复杂性的项目。项目经理应该使用下列哪项工具或技术来准备估算?
At the beginning of a project,a project manager must prepare a quick,high-level cost estimate. The project manager previously worked a project of similar size and complexity. What tools and techniques should the project manager use to develop the estimate?


A.专家判断和类比估算 Expert judgment and analogous estimating.

B.自下而上估算和储备分析 Bottom-up estimating and reserve analysis.

C.三点估算和质量成本(COQ) Three-point estimating and cost of quality(COQ).

D.自上而下估算和制定决策 Top-down estimating and decision making.


知识点:PMP强化练习题(二)


参考答案:A


解析:PMBOK(6)P244- 7.2.2.2 类比估算。成本类比估算使用以往类似项目的参数值或属性来估算。做过类似的项目,可以采用类比估算。