在审查所有项目的财务业绩时,项目管理办公室(PMO)提出对一个项目感到担忧,根据项目所有者和干系人的反馈,项目经理确信项目表现良好。项目经理可以应用哪一个指标来量化其假设?
While reviewing the financial performance of all projects,the project management office (PMO) raises one project as a concern. The project manager is confident that this project is performing well based on project owner and stakeholder feedback. What metric should the project manager apply to quantify their assumption?Earned value (EV)?


A.成本绩效指数(CPI) Cost performance index(CPI).

B.财务绩效 Financial performance.

C.挣值(EV) Earned value(EV).

D.成本基准对比 Cost baseline comparison.


知识点:PMP强化练习题(二)


参考答案:A


解析:PMBOK(6)P257-7.4 控制成本。项目财务业绩,即项目目前为止是超支了还是节约了,这个可以从CPI看出来。BD没有这种项目指标,C不能单独判断。