在一个工厂的项目建议书谈判期间,客户通知项目经理需要进行一项变更来提高性能。项目经理该怎么做?
During project proposal negotiations for an industrial plant, the customer informs the project manager that a change is required to improve performance. What should the project manager do?
A.让项目发起人增加额外资金 Ask the project sponsor for additional funding.
B.征求高级管理层的建议 Call senior management for advice.
C.更新工作分解结构(WBS) Update the work breakdown structure (WBS).
D.修订风险应对计划 Revise the risk response plan.
参考答案:B
解析:“项目建议书谈判期间”,项目的启动阶段,基准尚未形成,此时收到的变更请求通过协商的方式来解决,排除C选项。 选项A:是否增加依据协商的结果。 选项D:还未进入到规划阶段。