项目经理确定项目的进度绩效指数(SPI)为1.2,成本绩效指数(CPI)为0.8。项目目前的状态是什么?
A project manager determines that the a project's schedule performance index(SPI)is 1.2,and its cost performance index(CPI)is 0.8.What is the project a current status?
A.落后于进度,但低于预算 Behind schedule and under budget.
B.超前于进度,并低于预算 Ahead of schedule and under budget.
C.落后于进度,并超出预算 Behind schedule and over budget.
D.超前于进度,但超出预算 Ahead of schedule and over budget.
参考答案:D
解析:PMBOK(6),P261,7.4.2.2挣值分析。SPI大于1,进度提前;CPI小于1,成本超支。