团队开发和测试了新的软件,以控制飞行中的飞机。必须满足几项监管要求。项目经理应该做些什么来满足这些要求呢? A team has developed and tested new software to control airplanes during flights. There are several regulatory requirements that must be met. What should the project manager do to meet these requirements?
A.确定与遵守法规有关的潜在威胁。 Determine potential threats regarding compliance with the regulations.
B.要求人力资源(HR)为团队指派一名合规专家。 Ask human resources (HR) to assign a compliance specialist to the team.
C.验证软件符合标准和法规。 Validate that the software is compliant with standards and regulations.
D.衡量项目符合法规的程度。 Measure the extent to which the project complies with the regulations.
参考答案:C
解析:选C,为了满足监管要求,有必要验证软件是否符合适用的标准和法规。这可能需要与监管机构接洽,获得必要的认证,并确保软件符合所有相关的合规标准。选项A和D与确定和衡量项目的合规性有关,但不涉及确保合规性所需的实际步骤。选项B在某些情况下可能有用,但可能不必要或不足以确保遵守特定法规。