项目经理希望从最近完成的一个项目中复制良好实践。然而,项目经理在有时间评估最近完成项目的项目信息之前就已经开始负责管理另一个项目。项目经理应该怎么做?
A project manager wants to replicate good practices from a recently completed project. However, the project manager assumes another project before having time to assess the previous project’s information. What should the project manager do?


A.遵从分配调到新项目 Move to the new project according to assignment.

B.召开实施后评审会议 Conduct a post-implementation review meeting.

C.与新团队分享之前项目的经验教训 Share the lessons learned from the previous project with the new team.

D.要求项目管理办公室(PMO)和过程经理收集经验教训 Ask the project management office(PMO)and the process manager to collect the lessons learn


知识点:PMP强化练习题(二)


参考答案:B


解析:PMBOK(6),P121,4.7 结束项目或阶段。 “复制良好实践”,首先需要总结经验教训,选项实施后评审会议,就是项目后评价,也就是在做总结经验教训。符合题意,其他选项:经验教训要项目经理主导,排除D,C与A都在B的后面