一位项目团队成员临时离开项目,由具有类似技术技能的资源代替,由于新资源未参加过往项目会议,导致项目中断,项目经理应向新资源提供什么?
A project team member temporarily leaves the project and is replaced by resources with similar technical skills. Since the new resources have not participated in past project meetings, resulting in project disruption, what should the project manager provide to the new resources?


A.项目绩效报告 Project performance report

B.定期培训以及项目文档的访问权 Regular training and access to project documents

C.项目管理计划,包括范围和进度基准 Project management plan, including scope and schedule

D.工作绩效报告 Work performance report


知识点:PMP强化练习题(二)


参考答案:B


解析:PMBOK(6)P342- 9.4.2.6培训。一个新人加入进来了,需要进行团队建设,培训是团队建设的工具,确保新人快速上手工作。 其他选项:AD是给领导看的,C光看基准还不行,还需要增强技能。