“微信扫一扫”进入"可可试卷"微信小程序刷题
项目经理希望确保干系人能充分参与项目的整个生命周期,项目经理应该在干系人参与计划中包含下列哪一项?
A Project manager want to ensure sufficient stakeholder participation throughout a project’s in cycle. What should the project manager include in the stakeholder engagement plan?
A.干系人的权力/利益方格 Stakeholder power/interests grid
B.由干系人提出的变更请求 Change Request initiated by Stakeholders
C.期望的当前干系人参与水平 Desired and current stakeholder engagement levels
D.干系人对项目运作的反馈 Feedback from stakeholder on project operations
参考答案:C
解析:PMBOK(6)P521- 13.2.2.5数据表现。要想确保一个干系人参与,则需要对比他现在的参与水平和期望的参与水平,这个对比的工具就是干系人参与度评估矩阵。 其他选项:A在干系人登记册里,不在参与计划里。BD都不在参与计划里。