一个项目正在进行迭代设计阶段。其中一个团队成员的表现不佳。这是公司的一项关键项目,执行即将开始。项目经理应该做什么?A project is going through its iterative design stage. One of the team members has been performing poorly. This is a critical project for the company and execution is about to start. What should the project manager do?


A.关于团队成员的不佳表现,请求职能经理采取行动Request action from the functional manager regarding the team members poor performance

B.避免在下一个有迭代设计阶段的项目中选择这个团队成员Avoid selecting the team member to the next project that has an iterative design stage

C.在迭代设计阶段向团队成员提供反馈和辅导Provide feedback and coach the team member during the iterative design stage

D.将问题升级到人力资源经理,并要求替换团队成员Escalate the issue to the human resources manager and request that the team member be replaced


知识点:PMP强化练习题(一)


参考答案:C


解析:在敏捷项目中,项目经理有责任持续促进团队成员的成长和发展,选C。