项目管理专业人士资格认证(PMP)题库(1459题)


一家供应商被聘请为项目提供信息安全服务。供应商已经决定不再提供这项服务,因为他们没有按时付款。他们的服务至关重要,这个决定将影响项目的结果。项目经理应该做些什么来解决这个问题?A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project. What should the project manager do to ad dress this issue?


A.与供应商协商付款,并提醒他们长期合作。Negotiate the payments with the supplier and remind them of their long-term association.

B.根据合同的服务水平协议(SLA)对供应商进行处罚。Penalize the supplier according to the contract's service level agreement(SLA).

C.聘请另一家信息安全供应商,并激励他们快速交付。Hire another information security vendor and incentivize them to deliver quickly.

D.告知相关干系人这一挑战并寻求他们的支持。Inform the relevant stakeholders of this challenge and seek their support.


知识点:PMP强化练习题(一)


参考答案:A


解析:A选项最佳,项目经理应该先和供应商沟通,了解情况,讨论解决方案,并努力和供应商保持良好的合作关系。