公司正在使用范围管理计划中定义的特定组件开发的预测型方法。由于定期变化的法规要求,开发团队要求利用敏捷方法。对于开发团队的要求,项目经理应该怎么做?A company is using a predictive approach for the development of a particular component as define d in the scope management plan. Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches. What should the project manager do about the development team's request?


A.提高额外财政资源的要求Escalate the request for additional financial resources

B.向项目管理办公室提出修改组织过程资产的要求Forward the request to the project management office (PMO) to amend the organizational process assets

C.请项目发起人批准实施新办法Ask the project sponsor to obtain approval for implementation of the new approach

D.分析在要求的方法下需要解决的需求Analyze the requirements that will need to be addressed under the requested method


知识点:PMP强化练习题(一)


参考答案:D


解析:遇问题先分析,再行动。选项ABC皆为动作,D在它们之前,选D。