项目管理专业人士资格认证(PMP)题库(1459题)


项目经理正在领导一个开发新的移动应用程序的项目。在一次非正式的交谈中,一个干系人要求项目经理在当前的冲刺中增加新的功能。项目经理应该怎么做?A project manager is leading a project to develop a new mobile application. During an informal conversation, a stakeholder asked the project manager to add new features to the current sprint. What should the project manager do?


A.要求干系人等待下一个冲刺计划。Request the stakeholder to wait until the following sprint planning.

B.在接下来的站立会议中讨论这个需求。Discuss this demand during the following standup meeting.

C.接受变更请求并协商时间表。Accept the change request and negotiate the time line.

D.让产品负责人与干系人讨论需求。Ask the product owner to discuss this request with the stakeholder.


知识点:PMP强化练习题(一)


参考答案:D


解析:产品负责人(Product Owner)负责管理产品待办事项列表,任何关于产品功能或需求的变更请求都应该首先与产品负责人讨论,由其评估并确定优先级。选D。