一个敏捷团队正在进行一个为期两周的冲刺,以实现商业价值。在冲刺开始后大约一周时,产品负责人意识到错过了一个法规合规要求。产品负责人提醒团队,如果这个要求在当前冲刺中没有完成,组织将面临罚款。项目经理应该如何减轻这个风险?An agile team is working on a two-week sprint to deliver business value. About one week after the sprint starts, the product owner realizes that a regulatory compliance requirement was missed. The product owner reminds the team that this require ment must be completed in the current sprint or t he organization will face a penalty. What should th e project manager do to mitigate this risk?


A.与项目发起人回顾此问题,并请求更多时间来完成此要求。Review the issue with the project sponsor and ask for more time to complete this requirement.

B.完成影响分析,因为在冲刺开始后,冲刺待办事项列表的范围不能被更改。Complete an impact analysis as the scope of the sprint backlog cannot be changed after the sprint has started.

C.将合规用户故事包含在下一个冲刺中,因为团队正在忙于当前冲刺。Include the compliance user story in the next sprint as the team is fully occupied with the current sprint.

D.请求团队将用户故事添加到当前的冲刺中,并让他们开始工作。Request the team to add the user story to the current sprint and let them work on it.


知识点:PMP强化练习题(一)


参考答案:D


解析:合规大于天,在敏捷方法中,虽然在冲刺开始后一般不会更改冲刺待办事项列表,但面对重要的合规问题和可能的罚款,需要立刻采取紧急措施。