项目管理专业人士资格认证(PMP)题库(1459题)


在进行中的项目中,项目的主要联系人,也是客户,通知项目经理由于忙碌的日程将引入一个新的联系人。从现在开始,这位新的联系人也将参与重要决策。项目经理接下来应该采取什么行动?In an on going project, the customer, who has been the main contact for the project, informs the project manager that they will be introducing a new contact person due to their busy schedule. Moving forward, the new contact will also be making key decisions. What should the project manager do next?


A.更新干系人登记册,包括新联系人的详细信息。Update the stakeholder register with the new contact's details.

B.通知项目团队有关新的联系人。Inform the project team of the new point of contact.

C.更新沟通管理计划。Update the communications management plan.

D.请求与客户和新联系人的会议。Request a meeting with the customer and the new contact.


知识点:PMP强化练习题(一)


参考答案:A


解析:识别到新的干系人,首先更新干系人登记册。