一个新的政府法规规定,所有团队成员在下一个迭代的整个过程中都需要远程工作。这意味着需要完成产品待办事项的优先级变更。项目经理应该怎么做?A new government regulation has mandated that all team members will need to work remotely for t he duration of the next iteration. This means back log priority changes will need to be completed. What should the project manager do?


A.在下次回顾会议中将新的法规告知项目发起人。Communicate the new regulation to the project sponsor during the next retrospective.

B.尽快告知产品负责人所需的变更。Inform the product owner of the required change as soon as possible.

C.重新确定积压工作的优先级,并尽快与团队共享。Re-prioritize the backlog and share it with the team as soon as possible.

D.要求团队的协调者根据新的法规重新确定待办事项的优先级。Ask the team facilitator to re-prioritize the backlog based on the new regulation.


知识点:PMP强化练习题(一)


参考答案:B


解析:产品负责人负责管理产品待办事项优先级排序,当有外部环境有变化,可能影响项目或迭代的执行时,项目经理应尽快告知产品负责人,以便他们可以相应地调整和重新确定待办事项的优先级。