—个项目的规模已经大到由指导委员会取代单一的项目发起人。项目经理应该怎么做来适应这种新发展?
A project has become to large that the single sponsor is replaced by a steering committee.What should the project manager do to accommodate the new development?
A.认识到干系人结构发生了变化,并量身定做与这个团队的沟通 Recognize that there is a change in stakeholders structure and tailor communications to this group
B.按照最初的计划继续工作,同时认识到该项目现在包括其他干系人 Continue to work according to the initial plan while recognizing that the project now includes additional stakeholders.
C.为团队组织一次与新的指导委员会一起召开的会议,继续进行项目工作 Organize a meeting for the team with the new steering committee and continue work on the project
D.与新的委员会分享当前的状态报告 Share the current status report with the new committee
参考答案:A
解析:PMBOK(6)P529,13.3.3.2-项目管理计划更新:沟通管理计划和干系人参与计划。需要更新沟通管理计划,以反映新的或已变更的干系人需求。需要更新干系人参与计划,以反映为有效引导干系人参与所需的新的或更改的管理策略。题目中“由指导委员会取代单一的项目发起人”,干系人发生了变化,根据变化来跟新干系人沟通。B:干系人已经发生了变化,不能再按照原来的计划进行管理。C:采取适合的方式与新干系人沟通,会议只是一种沟通方式。D:不符合题意。