“微信扫一扫”进入"可可试卷"微信小程序刷题

项目管理专业人士资格认证(PMP)题库(1459题)


项目经理已经完成识别干系人的工作。之前,由于没有对项目经理和干系人的影响力或职权方面规定区别,项目经理在管理干系人方面有困难,在干系人登记册中需要包含哪一些信息?
A project manager has completed the identification of stakeholders.Previously,the project manager had difficulty managing stakeholders because no distinctions were made among them regarding influence or authority. What information needs to be included in the stakeholder register?


A.更新干系人的变更请求 Change requests for new stakeholders

B.干系人效益管理计划 Stakeholder benefits management plan

C.干系人参与计划 Stakeholder engagement plan

D.干系人分类 Stakeholder classification


知识点:PMP强化练习题(一)


参考答案:D


解析:解析:PMBOK(6)P514-13.1.3.1干系人登记册。干系人登记册中记录关于已识别干系人的信息,包括身份信息、评估信息和干系人分类等。 选项ABC:不记录在干系人登记册中。