项目经理从发起人处获悉,由于一项合同要求,必须为项目使用某项特定技术,项目经理发现,一名将被要求使用这项新技术的团队成员之前没有使用过这种技术的经验,公司限制禁止雇佣任何新的团队成员。项目经理应该做什么?
A project manager learns from the sponsor that,due to a contact requirement,a specific technology must be used for the project.The project manager discovers that one team member who will be required to use this new technology,has no previous experience working with it. What should the project manager do?


A.参考资源管理计划,以确定是否有该团队成员可以参加的已经规划好的培训 Refer to the resource management plan to determine if there is scheduled training in which the team member may participate.

B.增加该团队成员的任务持续时间,并相应地调整进度计划 Increase the team member's task duration,and adjust the schedule.

C.修改合同以允许使用不同的技术解决方案,以便所有团队成员都感到舒适 Revise the contract to allow for a different technology solution to be used so that all team members will feel comfortable.

D.将所有与该技术相关的任务委派给具有该技术经验的团队成员 Delegate all technology-related tasks to a team member who is experienced with technology.


知识点:PMP强化练习题(一)


参考答案:A


解析:PMBOK(6)P342- 9.4.2.6 培训。缺乏某一项技能,且不可雇佣新成员,安排培训来解决,培训在资源管理计划中规划。 其他选项:B直接增加时间不合适,C项目不是为了让成员舒适,D已经明确成员都没有经验了。