在施工阶段,一座城市的高端基础设施项目隧道部分遇到排水问题,项目团队正处于寻找解决方案的过程。更新问题日志之后,项目经理应该做什么?
During the construction phase, the tunnel part of a city's high-end infrastructure project encountered drainage problems, and the project team was in the process of finding a solution. What should the project manager do after updating the issue log?
A.请求预算补贴和延长进度计划 Request a budget allowance and schedule extension
B.与指导委员会沟通该问题,并提供定期进度更新,直至解决为止 Communicate the issue to the steering committee,and periodic progress updates until it is resolve
C.尽快解决问题,以避免进度计划延迟 fixing the problem to avoid a schedule delay as soon as possible
D.聘请一位外部顾问,就如何高效和经济有效地解决问题提供专家意见 Employ an external consultant to provide an expert opinion on how to efficiently and cost-effectively resolve the problem
参考答案:B