在定期的项目进度会议上,首席执行官通知项目经理,一个主要干系人不知道项目的最新进展。项目经理确保干系人已在干系人登记册中得到适当识别和分类。项目经理应审查哪个项目文件,以确定此问题的原因? During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The project manager is sure that the stakeholder was duly identified and classified in the stakeholder register. Which project document should the project manager review in order to determine the reason for this issue?
A.需求跟踪矩阵 Requirements traceability matrix
B.干系人登记册 Stakeholder register
C.干系人参与度评估矩阵 Stakeholder engagement assessment matrix
D.问题日志 Issue log
参考答案:C
解析:项目经理应审查干系人参与度评估矩阵(选项C),以确定干系人不了解项目最新发展的原因。干系人参与度评估矩阵用于记录每个干系人对项目的参与程度、影响和预期影响,并提供如何与每个干系人沟通的信息。