“微信扫一扫”进入"可可试卷"微信小程序刷题

项目管理专业人士资格认证(PMP)题库(1459题)


项目经理计划在一个月内部署一个全球性项目。但是,多名经理联系项目发起人,表示缺乏对项目可交付成果的认识。规划期间,项目经理应完成下列哪一项?
A project manager plans to deploy a global project in one month. However, several managers have contacted the project sponsor indicating a lack of awareness of project deliverables. What should the project manager have done during planning?


A.开展项目影响分析.安排进度活动并采取行动 Conducted a project impact analysis, scheduled activities, and taken actions

B.审查项目章程澄清范围 Reviewed project charter to clarify scope

C.安排每周风险审查会议 Scheduled weekly risk review meetings

D.识别项目干系人,并将其包含进沟通管理计划中 Identified project stakeholders and included them in the communications management plan


知识点:PMP强化练习题(一)


参考答案:D


解析:PMBOK(6)P366-10.1规划沟通管理。多名干系人表示缺少对项目可交付成果的认识,即干系人提出了对信息获取的要求,那么在规划阶段,项目经理要组织制定沟通管理计划。 选项AC:风险管理领域 选项B:范围管理领域