在一个价值100万美元的项目中途,项目经理进行挣值分析(EVA),分析显示计划价值(PV)为623,000美元,挣值(EV)为523,000美元,实际成本(AC)为643,000美元。 根据这些数字,项目的成本偏差(CV)和进度偏差(SV)分别是多少?
In midway of a US$1 million project, the project manager conducts an earned value analysis(EVA). The analysis shows a planned value (PV) of US$623,000, an earned value (EV) of US$523,000, and an actual cost (AC) of US$643,000.Based on these numbers, what is the project's cost variance (CV)and schedule variance(SV)?


A.CV =+120.000美元,SV =+100,000美元 CV = +US$120,000, and SV =+US$ 100,000

B.CV =+100.000美元,SV =+120,000美元 CV = +US$ 100,000, and SV - +US$ 120,000

C.CV =-100.000美元,SV = -120,000 元 CV = -US$100,000, and SV- -US$120,000

D.CV = -120.000美元,SV = -100,000美元 CV = -US$120,000, and SV--US$100,000


知识点:PMP强化练习题(一)


参考答案:D


解析:PV=623000,AC=643000,EV=523000,SV=EV-PV=-100000,CV=EV-AC=-120000