项目团队包括一名资源,但该资源同时致力于其他四个项目,项目经理得知该资源可能在计划的时间不可用。项目经理计划持续评估项目的进展,并根据该资源的可用性计划制定应急计划。这属于下列哪一项的实例?
The project team includes one resource, but the resource is dedicated to the other four projects. The project manager is aware that the resource may not be available at the planned time. The project manager plans to continuously evaluate the project progress and work out the contingency plan according to the availability plan of the resource. Which of the following items is an example of this situation?


A.接受风险 Accept risk

B.回避风险 Avoid risk

C.转移风险 Transfer risk

D.控制风险 Control risk


知识点:PMP强化练习题(一)


参考答案:A


解析:PMBOK(6)P442- 11.5.2.4威胁应对策略。制定应急计划属于风险接受。