项目团队正在研究一个项目的新批准范围,监管团队在变更方面提供的意见是不可或缺的。但是,该团队发现监管部门未被列为项目干系人。项目经理下一步应该怎么做?
A project team is working on a project’s new approved scope. The regulatory team was integral in providing input that necessitated this change. However, the team discovers that the regulatory department was not listed as a project stakeholder. What should the project manager do next?
A.指示项目团队确认是否需要进行这项变更 Instruct the project team to verify the need for this change.
B.创建一项新的变更请求并确保监管团队参与这个过程 Create a new change request and ensure that the regulatory team is involved in the process.
C.收集监管团队的进一步意见,并更新现有变更请求以反映新信息 Gather further input from the regulatory team and update the existing change request to reflect the new information.
D.确保监管团队包含在变更控制委员(CCB) 中 Ensure that the regulatory team is included in the change control boar
参考答案:B
解析:PMBOK(6)P535-13.4.3.2 监督干系人参与输出-变更请求。变更请求可能包括用于改善干系人当前参与水平的纠正及预防措施。监管部门未被列为项目干系人,干系人识别有问题,应该创建一个新的变更请求,还不是去直接更新现有的变更请求。 其他选项:A,由项目团队确认不正确。C不能直接就更新变更请求,应发起新的变更请求。D,没有B全面,要发起新的变更。