项目团队未能监督一项高风险,因此未能按时执行减轻措施,项目经理指示团队立即执行该措施,但另一位经理否决了这一指示,因为对项目没有造成负面影响。项目经理下一步应该做什么?
A project team failed to monitor a high risk,so the mitigation action was not performed on time. The project manager instructs the team to perform the action immediately, but anther manger overrules that since there was no negative impact. What should the project manager do next?
A.提交变更请求 Submit a change request.
B.询问团队未能监督风险的原因 Ask the team why the risk was not monitored
C.与团队一起重新评估风险 Reassess the risk with the team.
D.遵循经理的指示 Follow the manger's instructions.
参考答案:C
解析:PMBOK(6)P457- 11.7.2.3 风险审查会。在风险审查中,还可以识别出新的单个项目风险(包括已商定应对措施所引发的次生风险),重新评估当前风险。此风险没有影响,需要重新评估此风险。 其他选项:先重新评估,再采取AD的措施。B后面再说。