一个关键的项目决策需要所有干系人的支持。项目经理现在得知之前未识别到一名关键干系人。项目经理应该做什么来防止这个问题成为项目进展和成功的障碍?
A key project decision requires the support of all stakeholders. The project manager now learns that one key stakeholder was not previously identified. What should the project manager do to prevent this from being an obstacle to the project's progress and success?
A.审查干系人登记册 Review the stakeholder register.
B.与项目发起人会面 Meet with the project sponsor.
C.更新干系人参与评估矩阵 Update the stakeholder engagement assessment matrix.
D.定期及时审查沟通策略 Conduct regular and timely reviews of the communication strategy.
参考答案:C