项目需要一位熟练的工程师来执行某个特定任务,但由于工作量大,该工程师不能参与这个项目。项目经理下一步应该怎么做?
A project requires a skilled engineer to perform a specific task.However?due to high workloads,the engineer cannot participate in the project. What should the project manager do next?
A.修改进度计划,以适应该资源 Modify the schedule to accommodate the resource.
B.与职能经理协商该资源的参与 Negotiate with the fictional manager for the resource's participation.
C.培训项目团队中的某个成员来执行所需的活动 Train someone on the project team to perform the needed activity.
D.要求发起人提供更多的时间来寻找其他资源来执行任务 Ask the sponsor for more time to find another resource to perform the task.
参考答案:B
解析:PMBOK(6)P332- 9.3.2.2人际关系与团队技能-谈判。获取资源,优先进行谈判。 其他选项:本题是获取资源的过程,优先采用谈判。因此ACD都是谈判无果的情况下再采取的行动。