你是一款新的汽车应用程序的Scrum主管,该应用程序可检测汽车故障并将其报告给服务中心。在下一个冲刺开始之前,产品负责人希望编写一份清单,列出团队在当前冲刺结束时需要完成的工作类型。满足此标准意味着该工作是可交付的。此外,此清单应作为验收标准,适用于此冲刺中的产品待办事项。产品负责人试图确定什么内容?
You’re a scrum master for a new automotive app that detects car faults and report them back to the service center. Before the start of the next sprint, the product owner wants to write a checklist of the types of work that the team is expected to complete by the end of the current sprint. Meeting this criterion means that the work is potentially shippable. Besides, this checklist should serve as an acceptance criterion that applies product backlog items within this sprint. What is the product owner trying to define?


A.冲刺目标 Sprint Goal

B.准备就绪(DoR)的定义 Definition of Ready (DoR)

C.完成的定义(DoD) Definition of Done (DoD)

D.项目退出标准 Project Exit Criteria


知识点:PMP敏捷专项练习题(一)


参考答案:C


解析:敏捷实践指南,P151 完成的定义(DoD)是团队需要满足的所有标准的核对单,只有可交付成果满足该核对单才能视为准备就绪可供客户使用。从题目当中的关键字“编写一份清单”“作为标准”可得出,此处负责人想要确定的是完成的定义(DoD)。