在项目的第一个阶段发布给客户的最新软件充满了缺陷。客户很生气,并要求计划在第二阶段交付的新版本的开发过程更加透明。客户希望更有规律地看到团队的结果,而不需要很长的开发间隔。 项目团队可以在第二阶段引入下列哪项来更好地满足客户的要求? (选择四个)
The latest software released to the customer in the first project phase is full of defects. The customer is angry and demands that the development of the new release, which is planned to be delivered in the second phase, is much more transparent. The customer wants to see the team’s results more regularly and without very long development intervals in-between. Which of the following could the project team introduce in the second phase to better comply with the customer's demand? (Choose four)


A.有规律时间框的节奏 A cadence with regular timeboxes

B.定期和频繁的回顾 Regular and frequent retrospectives

C.在每个团队成员的层次上进行优化 Optimization at the level of each individual team member

D.测试驱动的开发实践 Test-driven development practices

E.使用待办事项列表进行增量交付 Incremental delivery using a backlog

F.在软件发布之前限制更改的数量 Limiting the number of changes before the software is released


知识点:PMP新模考(一)


参考答案:ABDE


解析:知识点出处:敏捷实践指南 页码:P9 章节:2.2 敏捷的12条原则 排除法:C:敏捷注重团队协作,而非单兵作战;F:敏捷拥抱变化。