有一部分项目工作从外部资源采购,项目团队制定采购计划,并向多个供应商发出建议邀请书,团队从潜在供应商那里获得关于工作的询问,为向潜在供应商提供响应,项目团队应该怎么做?
A portion of the project work is sourced from external sources, the project team makes the purchase plan and sends out a proposal invitation to multiple vendors, the team obtains inquiries about the work from the potential suppliers, and what the project team should do to provide responses to potential suppliers.
A.向每一位供应商发送单独回复 Send a separate reply to each supplier
B.在项目团队中为每一位供应商指定单个联系人 Assign individual contacts to each vendor in the project team
C.修订建议邀请书,将对所有问题的回复包含在内,并分发给所有供应商 Revised proposal invitation to include responses to all questions and distribute to all suppliers
D.召开投标人会议,澄清所有供应商的全部问题 Convene a meeting of bidders to clarify all suppliers' issues
参考答案:D
解析:知识点出处:PMBOK 6th 页码:P487 章节:12.2.2.3 投标人会议:投标人会议(又称承包商会议、供应商会议或投标前会议)是在卖方提交建议书之前,在买方和潜在卖方之间召开的会议,其目的是确保所有潜在投标人对采购要求都有清楚且一致的理解,并确保没有任何投标人会得到特别优待。 投标人会议两个作用:确保对采购要求的理解;保证公平。