一个敏捷团队在最近的几次迭代中加班加点地工作。项目经理决定,从现在开始,团队应该保持每周40小时的工作时间。项目经理做出这个决定最可能的目的是什么?
An agile team has been working overtime for the last few iterations. The project manager has decided that from now on the team should maintain a 40-hour workweek. What is the most likely reason behind the project manager's decision?
A.最大化未完成的工作量 To maximize the amount of work not done
B.最小化在进行中的工作量 To minimize the amount of work in progress
C.频繁交付工作软件 To deliver working software frequently
D.促进可持续发展 To promote sustainable development
参考答案:D
解析:知识点出处:敏捷实践指南 页码:P9 章节:2.2 敏捷的12条原则之8:敏捷过程提倡可持续开发。发起人、开发人员和用户应该都能始终保持步调稳定。