一位先前不活跃的干系人参与程度突然增加,这种意外的参与导致了一些变更请求。项目经理应该做什么?
The involvement of a previously inactive interested party suddenly increased, and this unexpected participation led to some change requests. What should the project manager do?
A.向干系人解释变更请求过程 Explain the change request process to interested parties
B.审查已批准的有关干系人请求的期望 Review approved expectations regarding stakeholder requests
C.与该干系人开会,以评估变更请求 Meet with the interested party to evaluate the change request
D.要求干系人与发起人讨论这些请求 Ask interested parties to discuss these requests with the sponsor
参考答案:C
解析:知识点出处:PMBOK 6th 页码:P113 章节:4.6 变更流程:变更提出后,先分析影响,再提交含解决措施的变更请求给CCB。审批前,三步骤提出变更-分析影响-提交审批。