在开发一个新产品时,耐久性测试是关键路径上的一项重要活动。然而,测试设施被一个优先级较高的项目占用,且占用时间比原计划长。项目经理接下来应该怎么做?
In the development of a new project the endurance testing is an important activity on the critical path. However, the last facility is occupied by a higher project. Which is taking longer than initially planned. What should the project manager do text?


A.为延迟的项目开展根本原因分析 Perform a root cause analysis for the delayed project

B.审查风险登记册中的适当响应 Review the risk register for the appropriate response

C.将延期情况通知项目干系人 Inform the project stakeholders about the delay

D.将问题上报给高级管理层 Escalate the issue to senior management


知识点:PMP新模考(一)


参考答案:B


解析:知识点出处:PMBOK 6th   页码:P455 章节:11.7.1.2 风险登记册: •已识别单个项目风险 •风险责任人 •商定的风险应对策略 •以及具体的应对措施 遇风险,先查册。