一个敏捷项目已经进入了第七次冲刺阶段。在冲刺结束前两天,客户通知产品负责人,他们忘记在冲刺中包含某个功能。高级经理无意中听到谈话,并表示包含该功能意味着范围蔓延,并不应被允许。产品负责人的最佳行动方案是什么?
An agile project has entered its seventh sprint. Two days before the end of the sprint, the customer informs the product owner that they forgot to include one feature in the sprint. A senior manager overhears the conversation and states that including the feature represents scope creep and should not be allowed. What is the product owner's best course of action?
A.与客户合作,在产品待办事项列表中为该功能设优先级 Work with the customer to prioritize the feature in the product backlog
B.请求客户提交变更请求 Request that the customer submit a change request
C.指导团队在当前的冲刺中开发该功能 Instruct the team to develop the feature in the current sprint
D.按照高级经理的指示拒绝该功能 Reject the feature as instructed by the senior manager
参考答案:A
解析:知识点出处:敏捷实践指南 页码:41 章节:4.3.2 产品负责人 Product Owner: 创建待办列表并排序 、确认工作优先顺序、 提供反馈、 指导开发方向 敏捷拥抱变更, PO与客户一起确认优先级。