在某个软件开发项目中,卖方已经按照合同要求圆满地完成了项目工作,这时,买方又要求在合同中添加一项新工作。鉴于上述情况,卖方应该如何做?
In a software development project, the seller has successfully completed the project work in accordance with the requirements as specified in the contract. At this point, the buyer requests to add a new work in the contract. Given this, what should the seller do?


A.开始合同收尾,并要求就新工作签订新合同 To proceed with the contract closing and to request a new contract for the new work

B.同意添加新工作,但要求用成本补偿的方式来做 To agree to add the new work, but request the cost reimbursement

C.拒绝做新工作,因为合同已经完成 To refuse to do new work because the contract has been completed

D.立即开展新工作,以便维护与买方的良好关系 To immediately start the new work to maintain a good relationship with the buyer


知识点:PMP新模考(一)


参考答案:A


解析:知识点出处:PMBOK 6th 页码:P121 章节:4.7 项目已经完成,可以正常进入收尾。买方有新的工作要求,可以签订新的合同。