“微信扫一扫”进入"可可试卷"微信小程序刷题
你正在管理一个项目,该项目将为你的客户提供电子学习解决方案。这个项目的需求在一开始并未明确定义,并且随着项目的发展会根据客户的反馈进行修改。你决定做尽可能多的计划,并在继续计划的同时开始创建工作。下列哪一种技术在定义项目活动时最有帮助?
You are managing a project which would provide e-learning solutions to your customer. The requirements of this project are not clearly defined in the beginning, and there would be modifications based on customer feedback as the project evolves. You decide to plan as much as you can and begin to create work while continuing the planning. Which of the following techniques would be most helpful while defining activities for the project?
A.滚动式规划 Rolling Wave Planning
B.模板 Templates
C.极限编程 Extreme Programming
D.准时制生产方式 Just in Time
参考答案:A
解析:知识点出处:PMBOK 6th 页码:P160 章节:5.4.2.2 滚动式规划:要在未来远期才完成的可交付成果或组件,当前可能无法分解。项目管理团队因而通常需要等待对该可交付成果或组成部分达成一致意见,才能够制定出 WBS 中的相应细节。这种技术有时称做滚动式规划。滚动式规划符合项目渐进明细的特点。C是软件开发技术而非项目规划技术。