scrum master 正在进行日常的站会。开发团队的每个成员都表示,由于各种阻碍,他们的工作已经停滞。因此,整个开发团队都被闲置,并且进度基准处于危险之中。scrum master 首先应该做什么?
A scrum master is conducting a daily standup. Each member of the development team states that their work has been stalled due to various blockers. As a result, the entire development team has been idled, and the schedule baseline is in jeopardy. What should the scrum master do first?
A.在会议期间努力解决问题 Attempt to resolve the problems during the meeting
B.分析并优先设置阻碍的优先级 Analyze and prioritize the blockers
C.与此同时让团队参与另一个项目 Assign the team to work on another project in the meanwhile
D.将该问题升级上报给项目发起人 Escalate the issue to the project sponsor
参考答案:B
解析:知识点出处:敏捷实践指南 页码:P34 章节:4.2.1 仆人式领导的职责:仆人式领导通过管理关系,在团队内和组织中建立沟通与协作。这些关系可以帮助领导在组织中得心应手地为团队提供支持。这种支持有助于消除障碍,促进团队理顺过程。 在敏捷实践中,项目经理重要的核心工作就是消除障碍。