项目发起人通知项目经理一项新的政府法律被批准了,该法律将影响项目的进度计划和预算,这种可能性作为一种主动接受的威胁包含在风险管理计划中。 项目经理下一步应该做什么?
The project sponsor informs the project manager that a new government law has been approved that will affect the project's schedule and budget, and this possibility is included in the risk management plan as a proactively accepted threat.What should the project manager do next?
A.更新风险管理计划,并记录经验教训 Update the risk management plan and record lessons learned
B.向变更控制委员会(CCB)提交一份变更请求 Submit a change request to the Change Control Board (CCB)
C.使用应急储备来管理这种情况 Use emergency reserves to manage this situation
D.评估管理储备来控制该风险 Assess management reserves to control the risk
参考答案:C
解析:知识点出处:PMBOK 6th 页码:P443 章节:11.5.2.4 接受风险:接受是指承认威胁的存在,但不主动采取措施。接受策略又分为主动或被动方式。最常见的主动接受策略是建立应急储备。被动接受策略则不会主动。 最常见的主动接受策略是建立应急储备。