由于缺乏供应商支持,实施了将一个外部软件模块替换成内部模块的权变措施。在没有供应商答复的计划日期下,项目经理应该怎么做?
Due to lack of supplier support, a workaround to replace an external software module with an internal module is implemented. What should the project manager do as there is no planned date replied by the supplier?
A.等待供应商的答复,并将该问题上报给项目发起人 To wait for the supplier's response and report the issue to the project sponsor
B.将该权变措施作为一项变更请求提交给变更控制委员会(CCB) To submit the workaround as a change request to the Change Control Board (CCB)
C.遵循范围管理计划 To follow the scope control plan
D.更新问题日志 To update the Problem Log
参考答案:B
解析:知识点出处:PMBOK 6th 页码:P457 章节:11.7.3.2 变更请求:执行监督风险过程后,可能会就成本基准和进度基准,或项目管理计划的其他组件提出变更请求,应该通过实施整体变更控制过程(见 4.6节)对变更请求进行审查和处理。 权变以后,需要提交变更请求。